This project will widen Ragsdale Road between the intersection with Split Log Road and the Glen Ellen subdivision. The new roadway will be three-lane curb and gutter road with a center turn lane and intermittent raised median. A 10-foot bike/pedestrian path behind a five-foot grass strip would also be included and a six-foot sidewalk on the other side if sufficient land is available. The cost of this project is currently programmed at $13 million.
Timeline:
- FY 2022 – project design
- FY 2023 - right-of-way acquisition and construction
- FY 2025 – estimated project completion