The City of Brentwood opened its fifth fire station in January 2023.   this station located at 9551 Split Lot Road, will serve the rapidly growing southeast portion of Brentwood.  In 2018, City Commissioners approved plans to purchase the property for $685,000.  Construction began in the fall of 2021 and was completed in December 2022.

Design Highlights 

  • $8.6 million for building and fire truck
  • Two-bay, two story fire station
  • Meets modern fire station design standards
  • Located in the fast growing, southeast part of Brentwood
  • Approximately 10,000 square foot facility, located on two acres
  • Located close to neighborhoods to increase citizen engagement

 

Key Features

  • House single fire company
  • Three to four fire personnel on site daily
  • Individual bedrooms, bathrooms, and showers
  • State-of-the-art workout facility
  • Training room
  • Publicly accessible restroom and drinking fountain for trail users

 

NW_View_Option_Fire Station 5

 

Timeline:

2018 - Station 5 community meeting

October 2018 - City approves property purchase

Summer/Fall 2020 - Design team, TMP Partners, selected to begin preliminary design work

Dec. 10, 2020 - Preliminary designs presented to City Commission (VIDEO)

April 8, 2021 - Neighborhood meeting on Station 5 design (VIDEO)

September 10, 2021 - Groundbreaking event 

Fall 2021 - Construction began

December 2022 - Station grand opening

 

 Presentations

Fire Station #5 Community Meeting Presentation #1

Fire Station #5 Neighborhood Meeting Design Presentation #2